Sacyr, DST and ACA Clinch the Oiã to Soure High-Speed Rail Stretch as the Jury's Final Report Shuts Out Mota-Engil's Lusolav

The tender jury's final report confirms the 2.038 billion euro bid from Sacyr, DST and Alberto Couto Alves for the second stretch of the Lisbon to Porto line, Jornal de Negócios reports. IP expects to sign the concession in the first half of 2027.

Sacyr, DST and ACA Clinch the Oiã to Soure High-Speed Rail Stretch as the Jury's Final Report Shuts Out Mota-Engil's Lusolav
Pampilhosa station on the Linha do Norte, between Aveiro and Coimbra. Illustrative. Photo: Nuno Morão, CC BY-SA 2.0, via Wikimedia Commons

A consortium of the Spanish builder Sacyr and the Portuguese firms DST and Alberto Couto Alves (ACA) has won the contract for the second stretch of the Lisbon to Porto high-speed line, between Oiã, in the Aveiro district, and Soure, south of Coimbra. Jornal de Negócios reported on Thursday 26 November that the tender jury's final report confirms the award to the Spanish-Portuguese group, which offered the lowest price, and the exclusion of its only rival, the Lusolav consortium led by Mota-Engil.

The final report closes the evaluation stage of a tender that Infraestruturas de Portugal (IP, the state rail and road manager) had to run twice. It is not yet the contract. On its high-speed tenders page, IP says it expects the concession contract for Oiã to Soure to be signed in the first half of 2027.

A tender run twice

The Oiã to Soure concession covers the design, construction, financing, maintenance and availability of the line, the same model as the first stretch. IP first launched it on 26 July 2024, but that tender was scrapped because no valid bids came in. After the spending was approved again, IP relaunched it on 23 January 2026.

Two groups bid. In August, a preliminary jury report recommended Sacyr, DST and ACA and proposed excluding Lusolav, as ECO reported at the time, citing Jornal de Negócios. According to those reports, the winning bid scored 8.381 overall and came in at 2.038 billion euros, against 2.3 billion from Lusolav, which groups Mota-Engil with six other Portuguese builders. The jury found that Lusolav's bid did not conform to the tender documents, apparently because it offered an alternative to the reference solution drawn up by IP.

Lusolav fought the recommendation. During the ten-day hearing that followed, Jornal de Negócios reported, the consortium asked for its own bid to be evaluated and for Sacyr's to be excluded instead. The final report, on Thursday's account, upheld the jury's original position.

Where the line stands

The Oiã to Soure stretch is the second piece of the first phase of the line. The first, from Porto Campanhã to Oiã, was awarded to Lusolav on 10 October 2024, and its contract was signed on 29 July 2025 with AVAN Norte, the concession company Lusolav formed. Work on that stretch is reaching homes: in October the government declared the urgent expropriation of more than 900 plots in Ovar and Santa Maria da Feira, and this week Campanhã residents were told to be out in the first half of 2027.

The losing consortium is therefore the one already building the northern stretch, while the stretch through the Coimbra area goes to a group led by a Spanish builder. South of Soure, the Soure to Carregado stretch already has a conditionally favourable environmental impact statement from APA, issued on 2 July 2025, and in October IP was weighing whether to split it into two public-private partnerships.

After the preliminary report, Mota-Engil's chief executive, Carlos Mota dos Santos, told Jornal de Negócios that the consortium would contest it. Whether Lusolav now takes the final decision to court is not yet known.

Sources: Jornal de Negócios, 26 November 2026; ECO, 26 August 2026; Infraestruturas de Portugal, high-speed tenders page (all in Portuguese).